CONSTRUCTION ALERT: Cheek-Sparger/Jackson Road Roundabout

CONSTRUCTION ALERT:  Cheek-Sparger/Jackson Road Roundabout

The contractor started pouring a section of Central Drive at noon today. This will cause some disruption to traffic, as the work will require flagging vehicles at times to accommodate concrete trucks.

To keep the project on schedule and essentially completed by late February, pouring concrete today is critical. With sub-freezing temperatures headed our way, engineers were concerned about a significant delay in the project because lower temperatures, as forecasted, would prevent any concrete from setting up.

With construction at high levels throughout the DFW area, materials are in short supply. The city’s contractor scrambled to find a company that could provide materials today. We got word at mid-morning that materials were on the way.

We apologize for any inconvenience and we appreciate your patience and understanding while we work to complete the Cheek-Sparger/Jackson Road roundabout as soon as possible.