Bedford Road Work: Asphalt Milling
TexOp Construction, LP will begin the process of milling the roadway at Hospital Parkway, from SH 183 to Pipeline Road, on Monday, March 25, 2019. Motorists will experience various lane closures while the milling takes place from approximately 8:00a.m. to 5:00p.m. daily. Milling will continue until approximately Wednesday, April 3, 2019.
Following the milling process, Tarrant County will begin the street overlay process at the same locations identified below. The entire mill and overlay project is anticipated to be completed by Monday, April 22, 2019. For further information, please contact the Public Works Department at 817-952-2200.
DATE | TIME | LOCATION |
Monday, March 25 – Wednesday, March 27, 2019 | 8:00a.m. – 5:00p.m. | Hospital Parkway, from SH 183 to Pipeline Road |
Thursday, March 28 – Friday, March 29, 2019 | 8:00a.m. – 5:00p.m. | L. Don Dodson Drive, from Central Drive to Murphy Road |
Monday, April 1st – Wednesday, April 3, 2019 | 8:00a.m. – 5:00p.m. | Harwood Road, from Central Drive to Martin Drive |