Paving operations will continue next week on Glenview Drive, west of Honey Lane. Traffic on this portion of Glenview will be reduced to ONE-WAY, WESTBOUND ONLY daily, starting at 5 a.m. and ending at around 5 p.m. each day. All eastbound traffic will be detoured while paving operations are taking place. Motorists are encouraged to plan another route and avoid the area. Text Glenview to 888777 to be notified of project updates.
Also next week, work will continue on the reconstruction of Daniel Drive. It should take 2 to 3 weeks for crews to remove the old asphalt pavement on Daniel, stabilize the subgrade and lay the new asphalt pavement. After paving is complete on Daniel Drive, the contractor will move to Kirk Lane. Other upcoming projects include Post Oak Drive, Crystal Lane, Windhaven Road, Lake Side Circle and South Crest Drive. Prior to the street reconstruction work, upgrades are being made to the water and sewer lines located beneath the street and repairs are made to the curb and gutter, where needed.