Asphalt overlay maintenance continues next week with work scheduled on multiple residential streets. Crews mill the existing asphalt first and return within a few days to lay the new asphalt pavement. The schedule, which is subject to change, is found below.
Residents should receive door hangers from the contractor prior to work taking place. To prevent project delays, residents are asked to move their vehicles from the street on the days contractors will be working there. Typically, your driveway will be temporarily inaccessible only while fresh asphalt is being poured and compacted in front of it.
- Catchin Dr: overlay Nov. 3
- Vance Rd: overlay Nov. 4
- Carma Dr: overlay Nov. 4
- Lake View Cir: overlay Nov. 5
- Skylark Cir: overlay Nov. 6
- Ridge View Ct: overlay Nov. 6
- Riviera Dr: overlay Nov. 7
Milling will also take place on the following streets in preparation for their overlay during the second week of November.
- Victoria Ave: milling Oct. 31, overlay Nov. 10
- Circleview Ct: milling Oct. 31, overlay Nov. 10
- Devonshire Dr: milling Nov. 3, overlay Nov. 11
- King Arthur Ct: milling Nov. 3, overlay Nov. 12
- Royal Ct: milling Nov. 3, overlay Nov. 12
- Diamond Loch W: milling Nov. 4, overlay Nov. 12
- Richland Plaza Dr: milling Nov. 4, overlay Nov. 12 & 13
- Venice St: milling Nov. 4, overlay Nov. 13
- Charles St: milling Nov. 4, overlay Nov. 13
- North Hills Ct: milling Nov. 4, overlay Nov. 13