Construction Notice: Group 2 Water & Wastewater CIP
Echo Hill Drive 12”/10” Sanitary Sewer and Paving Improvements
From Chapman Drive to Hightower Drive
Starting on or within 10 days after September 8, 2025
We are finalizing traffic control plans, coordinating with Birdville/Keller ISD, and working with ATMOS Energy to begin the Group 2 CIP reconstruction project. Message boards will be placed about one week before work begins.
Note: ATMOS Energy will also be in the area on a separate project to replace gas lines along Quail Run Drive and Echo Hill Drive from Chapman Road to Hightower Drive.
Project Timeline
• Construction begins on or within 10 days after September 8, 2025
• Echo Hill Drive work estimated: September–November 2025
• Contractor: Quality Excavation, LLC (Aubrey, TX), awarded by City Council
• Work will occur in phases with road closures changing as needed
Project Scope
The project replaces and rehabilitates aging sanitary sewer lines and reconstructs paving:
• Sanitary sewer rehabilitation (Echo Hill & Quail Run)
• New paving and subgrade improvements
Project Phases
Phase 1 – September to November 2025
• Sanitary sewer by Quality Excavation (Echo Hill Dr: Chapman to Hightower)
• Gas line by ATMOS (Quail Run Dr)
• Closure: Chapman Dr & Echo Hill Dr intersection (partial)
Phase 2 – November 2025 (after Phase 1)
• Sanitary sewer by Quality Excavation (Quail Run Dr: Highcrest to Herschel)
• Gas line by ATMOS (Echo Hill Dr)
• Closure: Quail Run Dr & Highcrest Dr intersection (partial)
Phase 3 – Following Phase 2
• Asphalt paving and subgrade stabilization (Echo Hill & Quail Run)
Phase 4 – April 2026
• Work near Whitley Road Elementary, held until the end of the 2025–26 school year
• Hickory Hill Dr closure planned for summer break
Funding
• Total cost: $4,182,134.53
• Funded by the City of Watauga






