UPDATE (July 22, 3 p.m.): Crews encountered some issues on Mountainview Drive and have rescheduled the repaving to Thursday, July 24.

UPDATE (July 17, 9 a.m.): Reynolds Asphalt let the City know crews are able to repave Willow Bend Court and Chaucer Lane tomorrow, July 18, ahead of schedule. Again, if you have any questions or concerns, please reach out to Public Works at public.works@bedfordtx.gov or call 817-952-2200.

Over the next 10 days, Willow Bend Court, Chaucer Lane, along with Mountainview Drive and Court (starting in the 200 block) will be repaved. Today or tomorrow, affected residents should receive a doorhanger providing information related to the project. Reynolds Asphalt crews will mill Willow Bend Court and Chaucer Lane on Thursday (take the top two inches off), and Mountainview on Friday. Reynolds will return on Monday, July 21 to lay down fresh asphalt and continue until the project is done, weather depending. If you have any questions or concerns, please reach out to Public Works at public.works@bedfordtx.gov or call 817-952-2200.